Project Summary

P&P

Lloyds-P&P-2025 • Lloyd's Banking Group PLC

PM: paul.johnston@revvence.com

In Trouble Bidding
Start Date Jan 05, 2026
End Date May 29, 2026 112 days remaining
Description

A six-month, four-person MVP to deliver position-based workforce planning (People & Places) as the first connected continuous planning showcase, demonstrating Oracle’s skills-based planning and keeping ITQ/Workday out.

Tags & Classification
Project Location UK
Project Type Workflow-Planning
Engagement Type T&M
Industry Universal Bank
Client Type Tier 1 Bank
Effort Metrics
Target Days 340.0 days
Actual Days 0.0 days
Forecast Days 428.0 days
Total Forecast Days 428.0 days
Effort Progress 0.0%
Effort Forecast 125.9%
Overrun 25.9%
💼 Consultant Assignments
Loading...

Loading assignment data...

Project Status Notes

No notes yet

Add notes to track project status and updates
Project Documents

No documents yet

Add links to project-related documents and resources
Recent Activity
entries
Download Excel

No recent activity

Account
My Profile

DEV Tools